Rules of thumb for estimating materials

Design IRL Editorial · Figures checked 7 November 2026 · For owners checking a contractor's bill of quantities (BOQ) · How we make our guides

You don't need to calculate every bag of cement. A few rules of thumb are enough to spot a BOQ that is far too high or suspiciously low.

How to use these numbers

These rules apply to a low-rise RCC frame house and are per sq ft of built-up area (BUA). They are approximate. Sources disagree, soil and design change the steel, and your engineer's drawings always win.

Use them to ask questions. If a quote is 30% off these figures, ask the contractor to explain why.

The structure: cement, steel, sand, aggregate, bricks

MaterialPer sq ft of BUANotes
Cement0.4 bags0.35–0.40 single storey; 0.40–0.50 for G+1 or G+2
Steel4 kgRange 3.5–4.5 kg; some G+1 houses reach 5–5.5 kg
Sand1.2–1.8 cftSources disagree widely
Coarse aggregate1.35 cftRange 1.0–1.5 cft
Bricks5–5.5 bricks9 inch outer walls, 4.5 inch partitions

Finishes: tiles, paint and putty

  • Tiles: about 1.3 sq ft of tile per sq ft of BUA, covering floors and dado.
  • Paint: about 0.18 litres per sq ft of BUA overall, around 0.14 inside and 0.4 outside.
  • Interior emulsion covers about 120–170 sq ft per litre per coat. Economy paints cover less.
  • Water-based primer covers about 180–220 sq ft per litre per coat.
  • Putty quantities vary a lot by product. Read the pack or datasheet.

Check the tin

Coverage depends on the wall and the product. The manufacturer's datasheet is always more reliable than a thumb rule.

Allow for wastage

MaterialWastage allowance
Cement2–3%
Steel3–5%
Tiles5–10% (more for diagonal layouts)
Sand and aggregate8–12%
Paint2–5%

Small items such as binding wire, admixtures and consumables add another 8–12% of material cost. A BOQ with no allowance for these is incomplete.

Where the money goes

Materials are commonly 50–65% of the build cost and labour 30–45%. Within material cost, a widely used Indian split looks like this.

ItemShare of material cost
SteelAbout 18–25%
CementAbout 16%
SandAbout 12%
Coarse aggregateAbout 7–8%
Finishers: bricks, tiles, paintAbout 16–17%
Fittings: doors, windows, electrical, plumbing, sanitaryAbout 23%
This is a share of material cost, not of the total cost.

Checking a contractor's BOQ

  • Ask every bidder to quote against the same BOQ, so the lines can be compared one by one. A contractor who won't share a BOQ is a warning sign.
  • Multiply your built-up area by the rules above and compare totals for cement, steel and bricks.
  • Check that the BOQ names the grade or brand of each material, not just the quantity.
  • Look for a wastage allowance and a line for small items. Missing lines often reappear later as extras.
  • Check whether the rates include GST, cartage and unloading. Handling and lifting can add 1–2%.

Steel is where estimates differ most, because it depends on the structural design. If the steel figure looks high or low, ask your structural engineer to confirm it from the drawings.

Worked example: a 2,000 sq ft house

MaterialRough quantity
Cement800–1,000 bags
Steel8–9 tonnes
Sand2,500–3,600 cft
Coarse aggregateAbout 2,700 cft
Bricks10,000–11,000
TilesAbout 2,600 sq ft, plus 10%
PaintAbout 360 litres
Approximate, before wastage except where noted.

Prices for these materials change month to month and city to city. Get 2–3 quotes for steel and cement, and keep a 10–15% contingency in your overall budget.

Find the people

Sources

Most published cost figures come from firms that sell the work. We give ranges and you should get 2–3 quotes.

  1. Civil Connectors: estimating quantities and cost
  2. Houseyog: material estimation BOQ guide
  3. Houseyog: building material cost list
  4. Houseyog: hidden costs and wastage
  5. Construction Estimator India: cement per sq ft
  6. Construction Estimator India: hiring a contractor
  7. Nerolac: what is paint coverage
  8. NoBroker: how much paint a room needs
  9. Birla White: Primacoat primer leaflet

Your cart

Pick for your space

We’ll fit Room of the day, your cart’s alternatives and your budget to it.

Project type

Location

When are you starting?
What help do you need?Pick any

Saved in this browser. Join free to keep it on every device.

Rules of thumb for estimating materials - Design IRL