How much cement, steel and sand a house needs

Design IRL Editorial · Figures checked 7 November 2026 · For owners building a low-rise house who want to check material quantities and bills · How we make our guides

Cement and steel are the two biggest material bills in the structure of a house. A few per sq ft rules tell you roughly how much you need, so you can spot an estimate that is far off.

The rules of thumb

These figures are per sq ft of built-up area (BUA) for a low-rise RCC frame house on normal soil. They are for planning only. Your structural engineer's drawings and bar bending schedule give the real quantities.

MaterialPublished figureOur calculator uses
Cement (50 kg bags)0.40–0.45 bags0.4 bags
Steel (TMT bars)3.5–4.5 kg single storey; 4.5–5.5 kg G+1 or G+24 kg ground only; 4.75 kg G+1; 5.25 kg G+2 or more
Sand0.04–0.05 tonnes, about 0.9–1.1 cft1.2 cft
Coarse aggregate (20 mm)0.06–0.07 tonnes, about 1.3–1.6 cft1.35 cft
Bricks or blocks6–85.25 bricks
Per sq ft of built-up area, before wastage. Published figures are Houseyog's (2026), scaled from its 1,000 sq ft example; tonnes to cft is our rough conversion. The calculator then adds wastage: cement 3%, steel 4%, sand and aggregate 10%, bricks 5%.

Steel goes up with floors

Pick the number of floors in the calculator. It uses 4 kg of steel per sq ft for a ground-only house, 4.75 kg for G+1 and 5.25 kg for G+2 or more, in line with the published figures. Our brick count is on the low side of the published figures, so a real count may come out a little higher.

Why your numbers will differ

  • Floors. Each added floor puts more load on the columns and footings below, so steel per sq ft rises with height.
  • Seismic zone. Delhi NCR, much of north India, the Himalaya and the north-east are in the higher seismic zones. The design code asks for more ductile detailing there, which means more steel at joints.
  • Soil. Black cotton soil, filled land and soft coastal or alluvial soil can need deeper footings, a raft or piles. That adds concrete and steel below ground.
  • Design. Long spans, cantilevered balconies, large openings and a basement all add steel. A plain, column-on-grid plan uses the least.
  • Walls. AAC or fly ash blocks in place of red bricks cut mortar and the weight the frame carries.

So treat the table as a range to ask questions about, not a target. If a quantity is 30% away from it, ask the engineer or contractor why.

What to buy: grades and brands

MaterialWhat it isWhere it goes
OPC 53 grade cementOrdinary Portland cement. Gains strength fast.RCC: footings, columns, beams, slabs, where early strength matters
PPC cementPortland pozzolana cement, made with fly ash. Gains strength slowly, cracks less.Brickwork and plaster; suits hot climates and long-term durability
Fe 500 TMTThe common grade for housesColumns, beams, slabs and footings
Fe 500D TMTFe 500 with more ductility (the D)G+1 and G+2 houses and earthquake-prone areas
Fe 550 / Fe 550D TMTHigher strength, slightly costlierHeavier structures; only if your engineer specifies it
UltraTech's advice: choose PPC for durability and OPC for speed. No one cement type suits every stage. Steel grades as Houseyog describes them.

Established cement brands include UltraTech, ACC, Ambuja, Ramco and Dalmia. Common TMT brands include Tata Tiscon, JSW Neosteel and SAIL. A branded bar costs a little more than secondary steel, but its grade is more reliable. Whatever you buy, check for the BIS mark: IS 1786 for TMT bars, IS 269 for OPC and IS 1489 for PPC.

What these materials cost

MaterialUnitRough price, Nov 2026
Cement50 kg bag₹340–460, by brand and type
TMT steelkg₹58–76 (metros about ₹60–75, tier-2 about ₹58–72)
Sand (river or M-sand)cft₹45–95
Coarse aggregatecft₹38–65
Red clay brickseach₹7–12
Fly ash brickseach₹6–9
AAC blockseach₹60–90
Houseyog (2026) and our rate table. Steel and sand move month to month; check with 2–3 local dealers.

Sand is often sold by the ton or by the truckload, not by the cft. One tonne of sand is roughly 22 cft. River sand at ₹1,200–2,000 a tonne is about ₹55–90 per cft. M-sand at ₹900–1,500 a tonne is about ₹40–70.

Worked example: a 2,000 sq ft G+1 house

Take a ground plus first floor house with 2,000 sq ft of built-up area. Using the calculator's rules, with wastage added, the quantities and costs come out like this.

MaterialQuantityRough cost
Cement2,000 × 0.4 + 3% = 824 bags₹3.0–3.8 lakh
Steel2,000 × 4.75 kg + 4% = 9,880 kg₹5.7–7.5 lakh
Sand2,000 × 1.2 + 10% = 2,640 cft₹1.2–2.5 lakh
Aggregate2,000 × 1.35 + 10% = 2,970 cft₹1.1–1.9 lakh
Bricks2,000 × 5.25 + 5% = 11,025₹77,000–1.3 lakh
Total₹11.9–17.1 lakh, typically about ₹14.1 lakh
That is about ₹590–855 per sq ft of built-up area for the main structural materials alone.

Add a floor and the steel goes up. As a G+2 house of the same area, at 5.25 kg per sq ft, the steel is 10,920 kg with wastage, or ₹6.3–8.3 lakh. The total rises to about ₹12.5–17.9 lakh.

For scale, our rate table puts a standard house at about ₹1,800–2,450 per sq ft in most cities, so ₹36–49 lakh for this house. The five materials above are about a third of that. Labour, finishes, doors, windows, wiring and plumbing make up the rest.

Buying and checking

  • Ask the contractor for a bill of quantities (BOQ) that names the grade and brand of cement and steel, not just the quantity.
  • Buy steel against the engineer's bar bending schedule, not a lump-sum tonnage.
  • Weigh a sample bundle of steel at delivery, and check the brand and grade rolled onto the bars.
  • Check the manufacturing date on cement bags. Use cement within about three months, and store it off the floor, away from damp.
  • Check whether dealer rates include GST, cartage and unloading. They often don't.
  • Don't skimp on curing. Cheaper cement used well beats good cement cured badly.

Where not to save

Steel and cement in the frame can't be fixed later. Save on finishes if you must, not on the grade of steel or the number of bars.

Who to hire

A structural engineer designs the frame and gives the bar bending schedule. That is where the real steel and concrete quantities come from. Your contractor then buys against it, and a local dealer supplies the cement, steel and aggregates. On a turnkey contract, ask to see the dealer bills for steel and cement.

Find the people

Sources

Most published cost figures come from firms that sell the work. We give ranges and you should get 2–3 quotes.

  1. Houseyog: TMT steel price per kg and steel per sq ft
  2. Houseyog: building material cost list 2026
  3. UltraTech: difference between OPC and PPC cement

Your cart

Pick for your space

We’ll fit Room of the day, your cart’s alternatives and your budget to it.

Project type

Location

When are you starting?
What help do you need?Pick any

Saved in this browser. Join free to keep it on every device.

How much cement, steel and sand a house needs - Design IRL