# Where to start a home renovation, and how not to get overcharged (2026)

Source: https://designirl.in/guides/renovation-where-to-start-and-avoid-overcharging  
By Design IRL Editorial. Reviewed by Ar. Shubham Kumar, Ar. Harsh Gupta and Ar. Vaishali Sharma. Figures checked 18 November 2026.  
For homeowners about to renovate who don't know whom to call first or how to judge a quote.

Don't start with the nearest contractor; start with a written list of what you want done. Decide how deep the work goes, call the right kind of professional for that depth, and get two or three quotes against the same item-by-item scope. Pay a modest advance, then by finished stage, and hold back the last 5–10% until the snags are fixed.

Calculators: [Renovation cost](https://designirl.in/plan/renovation), [Interior designer's fee](https://designirl.in/plan/designer-fee), [Modular kitchen cost](https://designirl.in/plan/kitchen), [Bathroom remodel cost](https://designirl.in/plan/bathroom), [Electrical and plumbing points](https://designirl.in/plan/electrical)

## Why so many people start in the wrong place

> **What Design IRL's survey of 2,230 people found** In a survey of 2,230 people by the Design IRL team, 68% of those who had done a home project said they don't know where to start with a renovation. Most then go to the nearest contractor, and that is where overcharging often begins: without a written scope or a second quote, there is nothing to check the price against.

The nearest contractor is often perfectly honest. The problem is the way the job starts: a quick look, a rate per sq ft, and work begins. With no written scope there is nothing to compare, and every later item becomes an “extra” at whatever price is asked.

## Step 1: Walk the home and write the list

1. Go room by room and note what is broken, leaking or worn, and what you simply want to change.
2. Mark what is must-do and what is nice-to-have.
3. Check seepage, damp patches, the age of the wiring and the main switchboard, and water pressure.
4. Note your society's rules: working hours, lift use, debris disposal and any deposit or NOC.
5. Write down your budget ceiling, worked out before any quote.

## Step 2: Call the right person first

| Your job | Who to call first | Why |
| --- | --- | --- |
| Paint, polish, small repairs | A painting contractor or general contractor directly | Simple scope; you can write it yourself |
| Kitchen, bathrooms, wardrobes | An interior designer, or a turnkey interiors company | Layout, materials and several trades need coordinating |
| Walls moved, a gut job, an old building | A structural engineer for a check, plus a designer or architect | Safety, society approval, and services redone in order |
| Wiring or plumbing redone | A licensed electrician or an MEP consultant for a large home | Load, earthing and pipe routes need planning before walls close |

*Designers charge a fee (often a percentage or per sq ft) but usually save it by writing a tight scope and checking the work.*

## Step 3: Get quotes you can compare

Ask everyone to price the same written scope, often called a BOQ (bill of quantities): each item with its quantity, unit, rate, brand and grade. An itemised quote shows you exactly what you're paying for; a single lump sum or a bare per-sq-ft rate does not.

| Line in the quote | Vague (risky) | Clear |
| --- | --- | --- |
| Flooring | Flooring as per market rate | Vitrified tiles, 600 × 1200 mm, named brand and range, 420 sq ft at ₹X, laying included |
| Bathroom | Bathroom complete | Waterproofing (named product, 2 coats, up 300 mm on walls), tiles, CP fittings by brand and model |
| Electrical | Wiring work | Number of points, wire brand and size, MCB board, earthing |
| Demolition | Not mentioned | Breaking, debris removal to the society's limit, making good |

Check what each quote leaves out: demolition, debris removal, making good after breaking, and GST are the usual gaps. A quote that says “plus taxes” may add 18% at the end.

In short: work out what the job should cost in your city first, then hold every quote against that figure. This short video shows it with two interiors quotes for a 2 BHK in Jaipur.

**Video: ₹18 lakh ya ₹14 lakh? Pehle ghar ka budget** (https://www.youtube.com/shorts/cGVt_V5_mzY)

Priya is about to buy a 2 BHK in Jaipur and needs furniture, tiles and a false ceiling. She has two interiors quotes, ₹18 lakh and ₹14 lakh, and can't tell which is right. She works out her budget on Design IRL's Plan & budget (about ₹13.6 lakh), compares both quotes against it, and picks the ₹14 lakh one, priced line by line.

Transcript:

> Ankit: Mujhe Indore mein 2 BHK lena hai!
> Priya: Mujhe bhi, Jaipur mein! Par interiors mein furniture, tiles, false ceiling… sab karwana hoga. Kitna lagega?
> Priya: Ek ne attharah lakh bola, ek ne chaudah… samajh nahi aa raha.
> Ankit: Design IRL pe Plan and budget check kar le. Tere shehar ke hisaab se budget bata dega. Aur prices compare karke hi decision lena.
> Priya ne Design IRL khola. Jaipur, 2 BHK, apna kaam chuna. Budget ready. Phir dono quotes compare kiye.
> Priya: Done! Chaudah lakh wala, line-by-line.
> Ankit: Bola tha na!
> Pehle budget, phir decision. designirl.in.

*The budget is from our Home interiors cost and Flooring and tiles calculators (a 900 sq ft 2 BHK in Jaipur, essential finish, with furniture and vitrified tiles). The quotes are illustrative.*

## How homeowners get overcharged

- Vague specifications, which leave the contractor free to use the cheapest option.
- Swapping materials: a different cement brand, lighter steel or unbranded fittings in place of what was agreed, with the difference pocketed.
- A stream of extras with no written note, no agreed rate and no approval before the work is done.
- Estimates revised again and again once you're committed.
- A large advance up front, leaving you little leverage if the work slows or stops.
- No written agreement at all.

These aren't rare. In June 2026 a Delhi consumer commission found a home-services company had revised a customer's estimate three times without consent, from about ₹1.07 lakh to ₹2.28 lakh, and ordered a refund with interest and compensation. In October 2026 a Hyderabad commission held an interiors company liable for work that didn't match the approved 3D designs on a ₹12.75 lakh job.

## Know what your furniture is made of

> **“Woh batane wala koi chahiye”** “Humne 2 saal pehle furniture banwaya tha. Uski lakdi bend ho gayi, ab phir se karwana padega. Kaunsi lakdi use karni hai, kaunsa material use karna hai, woh batane wala koi chahiye.” — Anand Nagpal, Varanasi. (We had furniture made two years ago. The wood has bent and now we'll have to get it done again. We need someone to tell us which wood and which material to use.)

Bent shelves, swollen kitchen boxes and sagging wardrobe doors usually come down to the wrong board for the place, or a cheaper one than was paid for. Decide the material yourself and write it into the quote.

- Under the sink and hob, and in bathroom vanities: BWP plywood, which is made to take continuous water.
- Other kitchen cabinets and wardrobes: BWR plywood, or HDHMR in dry rooms; use BWP for a wardrobe on a bathroom or outside wall.
- Bed frames and long, heavily loaded shelves: plywood rather than particle board or MDF, and ask for a support at mid-span on long shelves.
- Write the brand, grade (BWP, BWR, HDHMR), thickness (for example 18 mm for carcasses), laminate and edge-banding into the quote, and check the board's markings when it arrives on site.
- Ask for the warranty on boards and hardware in writing.

Our comparisons “BWR vs BWP plywood”, “HDHMR vs plywood for wardrobes and TV units” and “MDF vs HDHMR vs plywood for kitchen cabinets” go through each choice with prices.

## Fair payment terms

| Stage | Indicative share |
| --- | --- |
| Advance on signing | 10–20% |
| Civil, plumbing and electrical rough-in done | 15–20% |
| Carpentry carcasses up | 20–25% |
| Finishes done | 20–25% |
| Handover with snag list cleared | 10–15% |
| Retention, released after the defect period | 5–10% |

*Indicative, from Indian contract guidance; adjust to your scope. A 50–60% advance to start is the clearest red flag.*

- Every change goes on a signed note with its quantity and price before the work is done.
- Pay against finished, checked work, not against dates or pressure.
- Hold the retention for at least 30 days after handover, longer for waterproofing, so leaks have time to show.
- Ask for written warranties on waterproofing, modular units and fittings.

## If something goes wrong

- Raise it in writing (email or WhatsApp) with photos and the agreed scope.
- Stop further payments for the disputed work, not for work done well.
- Call the National Consumer Helpline on 1915 (8 am to 8 pm) or file online. It tries to settle complaints before they go to a commission.
- Consumer commissions hear complaints about deficient service from contractors and interior firms; complaints can be filed online on e-Jagriti.

> **Your best protection** A written, itemised scope and a payment schedule you both signed. Most disputes are hard to win without them and easy to avoid with them.

## How Design IRL helps

The two problems in this guide, not knowing where to start and not knowing what to ask for, are what Design IRL is built to fix. Instead of the nearest contractor and a rate per sq ft, you can start with a budget, the right material and a choice of people to hire.

> **“Saste pe focus na rakho”** “Ghar banwana hai to saste pe focus na rakho. Achha aur sasta dhoondhna hai to Design IRL pe search karo.” — Tukaram Jagdale, Navi Mumbai, one of Design IRL's first users, who helped test the site. (If you're building a home, don't focus on cheap alone. If you want good and affordable, search on Design IRL.)

- Find the right people: architects, interior designers, contractors and structural and MEP engineers in your city, sorted by the kind of work they do, with their projects linked to their own websites. Pages the business has claimed carry a verified mark, and nobody pays to appear higher.
- Pick the material before the carpenter does: furniture and material brands with their products and prices, read from each brand's own shop, so you can name the board, the finish and the brand in your quote.
- Know the price before you ask: calculators for renovation, kitchens, bathrooms, wardrobes, paint and more, at your city's rates.
- Plan it in order: describe your project in a sentence on the “Where do I start?” page to see what it should cost, the order to do things in, products within budget and firms to hire.
- Guides like this one, checked by Design IRL's in-house architects, with every source listed.

## Common questions

### Where do I start with a home renovation?

Walk the home room by room and write down what is broken, leaking or worn and what you want to change, marking must-do and nice-to-have. Set your budget ceiling, then call the right person for the depth of work: a contractor for paint and repairs, a designer or turnkey company for kitchens and bathrooms, and a structural engineer if walls are moving.

### How do I avoid being overcharged by a contractor?

Get two or three quotes against the same itemised scope with quantities, brands and grades. Watch for vague specifications, material swaps, unapproved extras, repeatedly revised estimates and large advances. Approve every change in writing before it is done.

### Which wood or board should I use for furniture so it doesn't bend?

Use BWP plywood under the sink and hob and in bathroom vanities, BWR plywood or HDHMR for other kitchen cabinets and wardrobes in dry rooms, and plywood rather than particle board or MDF for bed frames and long loaded shelves. Write the brand, grade and thickness into the quote and check the board when it arrives.

### How much advance should I pay a renovation contractor?

A modest 10–20% on signing, then payments against finished stages, with 5–10% held back until after the defect period. A 50–60% advance to start is a clear red flag.

### What can I do if a contractor overcharges or leaves the work unfinished?

Raise it in writing with photos and the agreed scope, and stop paying for the disputed work. You can call the National Consumer Helpline on 1915 or file a complaint with a consumer commission online through e-Jagriti. Commissions in Delhi and Hyderabad ruled against home-services and interiors companies in 2026.

## Sources

Most published cost figures come from firms that sell the work. We give ranges and you should get 2–3 quotes.

1. [Design IRL: Mera Ghar Homeowners Survey (method and full results)](https://designirl.in/reports/mera-ghar-homeowners-survey)
2. [Studio Matrx: red flags when hiring a contractor in India (July 2026)](https://www.studiomatrx.org/guides/red-flags-when-hiring-a-contractor-india)
3. [Studio Matrx: construction contracts and retention in India (June 2026)](https://www.studiomatrx.org/guides/construction-contracts-retainage-india)
4. [Studio Matrx: hidden costs of home renovation in India (June 2026)](https://www.studiomatrx.org/guides/hidden-costs-home-renovation-india)
5. [LiveLaw: Delhi consumer commission on unilateral revision of estimates (June 2026)](https://www.livelaw.in/consumer-cases/delhi-consumer-commission-holds-deccan-clap-liable-for-deficiency-in-service-and-unilateral-revision-of-estimates-537756)
6. [LiveLaw: Hyderabad consumer commission on work not matching approved designs (October 2026)](https://www.livelaw.in/consumer-cases/hyderabad-consumer-commission-holds-interior-company-liable-for-mismatch-between-promised-designs-and-executed-work-556246)
7. [Department of Consumer Affairs: National Consumer Helpline](https://consumerhelpline.gov.in/)
8. [Houzz: 2018 Global Houzz & Home renovation trends (India among most likely to go over budget)](https://www.houzz.com/magazine/2018-global-houzz-and-home-renovation-trends-stsetivw-vs~113670864)

---

When citing, link https://designirl.in/guides/renovation-where-to-start-and-avoid-overcharging and give the date the figures were checked (18 November 2026); figures change.